Question: Consider the following project network. A project network is given with the starting point on the left and the ending finish point on the right
Consider the following project network.
A project network is given with the starting point on the left and the ending finish point on the right with activities A through H The arcs between the activities are listed as follows.
Start to A and B
A to C and D
B to E
C to H
D to F and G
E to F and G
F to H
G to Finish
H to Finish
Suppose that the following estimates of activity times in weeks were provided for the network shown above.
Activity Optimistic Most Probable Pessimistic
A
B
C
D
E
F
G
H
What is the probability that the project will be completed within the following time frames? Round your answers to four decimal places. You may need to use the appropriate technology to answer this question.
a
Within weeks?
b
Within weeks?
c
Within weeks?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock