Question: Consider the following project network, with task duration data provided: Which of the following are true statements, concerning tasks pictured in this diagram? 1. Task

Consider the following project network, with task duration data provided: Which of the following are true statements, concerning tasks pictured in this diagram? 1. Task D could be started immediately, even if no other work has been done on any other tasks. II. Task B cannot start until both tasks A and D are completed. III. Task J cannot start until both tasks E and I are completed. a. I and II b.I, II and III c. III only d. I only e. II and