Question: Consider the following project where times are in weeks Table 1. Activity times and predecessors ACTIVITY PREDECESSOR OPTIMISTIC TIME MOST LIKELY TIME PESSIMISTIC TIME VARIANCE
Consider the following project where times are in weeks
Table 1. Activity times and predecessors
| ACTIVITY | PREDECESSOR | OPTIMISTIC TIME | MOST LIKELY TIME | PESSIMISTIC TIME | VARIANCE |
| A | - | 5 | 12.5 | 23 |
|
| B | - | 9 | 12 | 15 |
|
| C | A,B | 4 | 6 | 11 |
|
| D | B | 3 | 4.5 | 6 |
|
| E | A | 4 | 8 | 12 |
|
| F | C | 5 | 8 | 11 |
|
| G | E,F | 5 | 6 | 10 |
|
| H | D,F | 2 | 3 | 4 |
|
| I | G,H | 3 | 3 | 3 |
|
| J | I | 2 | 3 | 7 |
|
Required
- Determine the Expected Time of each activity.
- Determine the activity schedule (ES, EF, LS, and LF) as well as slack. (10 marks)
- Determine and state the critical path for this project. This must be based on your work in c) and not by inspection.
- What are the expected time, variance and standard deviation of the project?
- What is the probability that the project will be completed in 35.5 weeks?
Please do it in word document... so the workings can be clearer. Thanks in advance
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock