Question: Consider the following projects: Cash Flows ($) Project A 4 5 2.3 0 0 1,000 B 5,600 2,800 2,800 5,800 2,800 2,800 C 7,000 2,800
Consider the following projects:
| Cash Flows ($) | ||||||
| Project | ||||||
| A | 4 | 5 | 2.3 | 0 | 0 | 1,000 |
| B | 5,600 | 2,800 | 2,800 | 5,800 | 2,800 | 2,800 |
| C | 7,000 | 2,800 | 2,500 | 0 | 2,800 | 2,800 |
|
| ||||||
what is payback period for project C?
A - 3.4
B - 3.6
C - 3.9
D - 3.8
E - 3.2