Question: Consider the following projects: Cash Flows, $ Project C 0 C 1 C 2 C 3 C 4 C 5 A 1,200 +1,200 0 0
| Consider the following projects: |
| Cash Flows, $ | ||||||
| Project | C0 | C1 | C2 | C3 | C4 | C5 |
| A | 1,200 | +1,200 | 0 | 0 | 0 | 0 |
| B | 2,400 | +1,200 | +1,200 | +4,200 | +1,200 | +1,200 |
| C | 3,000 | +1,200 | +1,200 | 0 | +1,200 | +1,200 |
| a. | If the opportunity cost of capital is 12%, what is the NPV for each project? (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations. Round your answers to 2 decimal places.) |
| b. | Calculate the payback period for each project. (Do not round intermediate calculations. Round your answer to 2 decimal places.) |
| Project | Payback Period |
| A | year(s) |
| B | year(s) |
| C | year(s) |
| Project | NPV | |||||||||
| A | $ | |||||||||
| B | $ | |||||||||
| C | $ | |||||||||
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
