Question: Consider the following projects (data in thousands): Project A B C D E F G Initial Cost 10 20 20 15 30 40 20 NPV
Consider the following projects (data in thousands):
| Project | A | B | C | D | E | F | G |
| Initial Cost | 10 | 20 | 20 | 15 | 30 | 40 | 20 |
| NPV | 1.1 | 3.6 | 0.8 | 1.6 | 4.0 | 3.0 | 1.4 |
If you are limited to $115,000 for initial costs for projects, which projects would you choose? Why?