Question: Consider the following projects for problems MC13 - MC15: YEAR 0 1 2 3 4 Project A -$500 $100 $150 $200 $250 Project B -$350
Consider the following projects for problems MC13 - MC15:
YEAR
0
1
2
3
4
Project A
-$500
$100
$150
$200
$250
Project B
-$350
$150
$150
$80
$80
Project C
-$800
$175
$250
$300
$350
The cost of capital for the firm is 10%.
What is the NPV for project A?
Consider the following projects for problems MC13 - MC15:
YEAR
0
1
2
3
4
Project A
-$500
$100
$150
$200
$250
Project B
-$350
$150
$150
$80
$80
Project C
-$800
$175
$250
$300
$350
The cost of capital for the firm is 10%.
What is the NPV for project A?
$35.89
$11.29
$10.10
$25.08
$30.15
Question at position 14 14 3 points
Question at position 14 Using the information in MC13, if the projects are mutually exclusive, what is your decision?
Using the information in MC13, if the projects are mutually exclusive, what is your decision?
Take project A only
Take project A, B, and C
Take project A and B only
Take project C only
Take project B only