Question: Consider the following projects: Project C 0 C 1 C 2 A $ 2 , 9 0 0 + $ 2 , 8 0 0

Consider the following projects:
Project C0 C1 C2
A $ 2,900+$ 2,800+$ 2,000
B 2,900+2,240+1,888
Calculate the profitability index for A and B assuming a 21% opportunity cost of capital.