Question: Consider the following scenario. For a construction project, there are three workers were assigned to complete the work. Right before the execution phase, one of

Consider the following scenario. For a construction project, there are three workers were assigned to complete the work. Right before the execution phase, one of the workers had COVID. He was removed from the project. The information on the activities is provided below. Use this information to develop a resource-constrained schedule in the loading chart by only using the available workers.
Activity# Immediate Predecessor (IP) Duration (D) Required Resources
A1--22
A2 A112
A3 A132
A4 A2, A312
A5 A422
A6 A431
A7 A522
A8 A6, A722
Hint:
Use the attached file template to provide the resource levelled plan. Once completed, upload the file as your response. Resource Constrained Schedule.xlsx Download Resource Constrained Schedule.xlsx
Use the CPM/PERT schedule as a baseline and determine resource requirements using the baseline plan created to perform the resource levelling.
No need to upload the Network Diagram.
Use heuristic rule minimum slack, smallest duration, and lowest activity identifier

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!