Question: Consider the following scheduling process: Task Time Preceding Task A 5 B C D E F G 6 A A B 7 9 10
Consider the following scheduling process: Task Time Preceding Task A 5 B C D E F G 6 A A B 7 9 10 6 4 B,C C D,E,F Perform a PERT analysis for this and answer the following: The total time needed for the completion of the project is = Expected answer format: 99 A/ The Critical path from the left to right is: Expected Answer format in each blank: X Enter only one alphabet per blank. If there are more blanks than needed, then simply enter '-' in the remaining blanks. A/ A A A A A/ A