Question: Consider the following sequential operating system. We have three workers (A, B and C) and two activities (1 and 2). Activity 1 can be done
Consider the following sequential operating system. We have three workers (A, B and C) and two activities (1 and 2). Activity 1 can be done by A in 3 min, or it can be done by B in 4 min; while Activity 2 can be done by C in 2 min. The resources and processing times for each activity are given below: (a) Which resource is the bottleneck? Whats the capacity of the process (units/minute)? [5 pts] (b) What is the (average) flow time? [5 pts] (c) What is the cycle time? [5pts] (d) What is the work-in-process inventory? [5pt]
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
