Question: Consider the following set of process from different users shown below in Table 1 to utilize the printer connected in ICT network Process P1 P2

Consider the following set of process from different users shown below in Table 1 to utilize the printer connected in ICT network Process P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 Table 1 Burst Time (ms) 8 5 6 32 76. 81 12 25 4 200 The processes are assumed to be arrived in the order of P1, P2, P3, P4, P5, P6, P7, P8, P9 and P10 at time 0. i) Draw the Gantt chart for illustrating the execution of these processes using Shortest Job (3] First (SJF) scheduling