Question: Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project

Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday). Assume no working-day holidays during the months of May and Juneno Memorial Day holiday, for example.

Activity Duration (days) Predecessor
A 5 --
B 5 A
C 10 A
D 4 A
E 5 B, C, D

On a piece of scratch paper, draw the Gantt Chart for the table above. Given that the Month of May has 31 days, what is the late start date for activity D?