Question: Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday). Assume no working-day holidays during the months of May and Juneno Memorial Day holiday, for example.
| Activity | Duration (days) | Predecessor |
| A | 5 | -- |
| B | 5 | A |
| C | 10 | A |
| D | 4 | A |
| E | 5 | B, C, D |
On a piece of scratch paper, draw the Gantt Chart for the table above. Given that the Month of May has 31 days, what is the late start date for activity D?