Question: Consider the following table of activities. Activity Predecessors Optimistic Time Most Likely Pessimistic (a) Time (m) Time (b) 6 10 14 IB 8 9 13

Consider the following table of activities.

Consider the following table of activities. Activity Predecessors Optimistic Time Most Likely Pessimistic (a) Time (m) Time (b) 6 10 14 IB 8 9 13 C 4 12 20 A ID 6 8 10 B.C What is the estimated time to complete the project? Select one: O 22 O 30 25 O 35