Question: Consider the following two projects. 0 1 2 3 |---------------------|-----------------------|----------------------| Project A: -1,000 500 500 280 Project B: -1,000 430 430 430 NPV Profile NPV
- Consider the following two projects.
0 1 2 3
|---------------------|-----------------------|----------------------|
Project A: -1,000 500 500 280
Project B: -1,000 430 430 430
NPV Profile
NPV
NPV1 Project B
Project A
NPV2
NPV3
r1 r2 r3 Projects cost of capital (= r)
- Find r1(crossover rate), r2, and r3. (9 pts)
- If the projects cost of capital is 10% and the projects are mutually exclusive (only highest NPV project should be chosen), what project do you have to choose? What if the projects cost of capital is 3%? (6 pts)
Please solve without excel and show formulas!