Question: Consider the following two projects and their respective cash flow profile of net benefits: Table 1: Net Cash flows of Benefits for Project 1 Year
Consider the following two projects and their respective cash flow profile of net benefits:
Table 1: Net Cash flows of Benefits for Project 1
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Net benefits | -500 | 450 | 500 | 520 | 600 | 650 | 700 | 800 | 200 |
Table 2: Net Cash flows of Benefits for Project 2
| Year | 4 | 5 | 6 | 7 | 8 | 9 |
| Net benefits | -400 | 150 | 200 | 300 | 400 | 150 |
- Assume that the interest rate in Year 1 is 11% and that it will decline by 1% every year until Year 6 and thereafter stay constant.
- By discounting the net benefits, calculate the net present values (NPV) of project 1 as of Year 1, 3 and 7,
- Find the net present values (NPV) of project 2 as of Year 1, 4 and 6.
- Again, assume that the interest rate in Year 1 is 1% and that it will increase by 1% every year until Year 6 and thereafter stay constant.
- By discounting the net benefits, calculate the net present values (NPV) of project 1 as of Year 1, 3 and7,
- Find the net present values of project 2 as of Year 1, 4 and 6.
Compare the results in questions 1 and 2 above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock