Question: Consider the following two projects: Project Alpha Beta Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount
Consider the following two projects: Project Alpha Beta Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Discount CIF C/F C/F C/F C/F C/ F C / F C /F Rate - 79 20 25 30 35 40 N/A N/A 13% -80 25 25 25 25 25 25 25 The net present value (NPV) for project beta is closest to: O A. $33 O B. $19 OC. $22 OD. $27