Question: Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash
Consider the following two projects:
ProjectYear 0
Cash Flow
Year 1
Cash Flow
Year 2
Cash Flow
Year 3
Cash Flow
Year 4
Cash Flow
Discount
Rate
A100405060N/A0.16B73303030300.16The profitability index for project B is closest to:
A.0.09
B.22.49
C.0.15
D.14.99