Question: Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow - 100 40 50 60 N/A -73 30 30 30 30 Discount Rate 0.14 0.14 A B The net present value (NPV) of project B is closest to: A. 15.9 B. 14.4 C. 36 D. 18