Question: Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash

Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A - 100 40 50 40 B - 73 30 30 30 30 N/A Discount Rate 0.13 0.13 The payback period for project A is closest to: O A. 2.3 years OB. 2 years OC. 2.7 years OD. 2.5 years