Question: Consider the following work breakdown structure: ActivityPrecedesTime Estimates ( days ) OptimisticMost LikelyPessimisticStartA,B AC , D 4 4 5 0 5 6 BD 4 5

Consider the following work breakdown structure:
ActivityPrecedesTime Estimates (days)OptimisticMost LikelyPessimisticStartA,BAC,D445056BD456075CE424548DF314049EF273639FEnd587082
What is the estimated expected (mean) time for project completion?
Multiple Choice
160 days
170 days
200 days
210 days
300 days