Question: Consider the matrix of sequence dependent setup times for three jobs, sjk=465847, and a given sequence job1-job2-job3 where process times are 17,10 , and 8

 Consider the matrix of sequence dependent setup times for three jobs,

Consider the matrix of sequence dependent setup times for three jobs, sjk=465847, and a given sequence job1-job2-job3 where process times are 17,10 , and 8 , respectively. sjk means that if job k follows job j there exists sjk amount of setup time. Compute the corresponding total flow time and makespan to this sequence when there is a single machine