Question: Consider the MPS, BOM, and inventory data shown. The following table shows the MPS start quantities for the next 10 weeks. Finished Item A 1
Consider the MPS, BOM, and inventory data shown.
The following table shows the MPS start quantities for the next 10 weeks.
| Finished Item A | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| MPS start time for Item A | 20 |
| 60 |
| 40 |
| 20 | 40 |
|
|
Bill of Material:
- Item A uses 2 units of component B, 1 unit of component C.
- Subassembly B uses 2 units of component D.
Selected Inventory Data:
| Item | Lot Sizing Rule | Lead Time | Scheduled Receipts | On-Hand |
| B | L4L | 1 | 80 in period 1 | 0 |
| C | FOQ = 50 | 2 |
| 40 |
| D | FOQ = 200 | 1 |
| 80 |
Construct the MRP schedule using the preceding information.
a) Draw the BOM
b) Complete MRP for Item B
c) Complete MRP for Item C
d) Complete MRP for Item D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
