Question: Consider the network below: A D E Start Finish B F Activity times are as follows (in weeks): Activity Normal Time Crash Time A 12

Consider the network below: A D E Start Finish B

Consider the network below: A D E Start Finish B F Activity times are as follows (in weeks): Activity Normal Time Crash Time A 12 8 B 14 10 8 8 D 5 3 E 4 3 F 6 5 G 10 8 There are activities on the critical path