Question: Consider the network below. Activity durations are given in nodes. What is free float of activity F? C,4 F,7 H,8 A,4 D,6 G,7 K,4 B,5

Consider the network below. Activity durations are given in nodes. What is free float of activity F? C,4 F,7 H,8 A,4 D,6 G,7 K,4 B,5 E,9 J,10 Select one: O a. 0 O b. 1 O c. 2 O d. 3