Question: Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Optimistic Probable J -- 15 8 10 K -- 9 7 8 L
Consider the network described in the table below.
| Activity | Immediate Predecessor(s) | Pessimistic | Optimistic | Probable |
| J | -- | 15 | 8 | 10 |
| K | -- | 9 | 7 | 8 |
| L | J | 10 | 5 | 6 |
| M | J | 3 | 3 | 3 |
| N | K, M | 9 | 1 | 5 |
| O | K, M | 11 | 3 | 7 |
| P | L, N | 11 | 2 | 8 |
- Draw the network diagram and fill out the chart below (by doing the forward and backward path analysis).
| Task | Expected Time | Variance | Early Start | Early Finish | Late Start | Late Finish | Slack Time |
| J |
|
|
|
|
|
|
|
| K |
|
|
|
|
|
|
|
| L |
|
|
|
|
|
|
|
| M |
|
|
|
|
|
|
|
| N |
|
|
|
|
|
|
|
| O |
|
|
|
|
|
|
|
| P |
|
|
|
|
|
|
|
2. Write the critical path and calculate the expected duration and standard variance of the critical path.
3. a. Calculate the probability that the project will be completed in fewer than 30 time units.
b. How much time does it need to finish the project by 90% chance?
4. Draw the Gantt Chart for this problem.