Question: Consider the network described in the table below. ( Round answers to two decimal places ) Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15
Consider the network described in the table below. (Round answers to two decimal places)
| Activity | Immediate Predecessor(s) | Pessimistic | Probable | Optimistic |
| J | -- | 15 | 10 | 8 |
| K | -- | 9 | 8 | 7 |
| L | J | 10 | 6 | 5 |
| M | J | 3 | 3 | 3 |
| N | M | 9 | 5 | 1 |
| O | K, M | 10 | 7 | 4 |
| P | L, N | 10 | 8 | 3 |
a) Calculate the expected duration, variance, ES, EF, LS, LF, and slack of each activity.
Use a table similar to the table below.
| Task | Early Start | Early Finish | Late Start | Late Finish | Slack | t | variance |
| J |
|
|
|
|
|
|
|
| K |
|
|
|
|
|
|
|
| L |
|
|
|
|
|
|
|
| M |
|
|
|
|
|
|
|
| N |
|
|
|
|
|
|
|
| O |
|
|
|
|
|
|
|
| P |
|
|
|
|
|
|
|
b) Calculate the expected duration and variance of the critical path.
c) Calculate the probability that the project will be completed in fewer than 24 time units.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
