Question: Consider the network described in the table below. ( Round answers to two decimal places ) Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15

Consider the network described in the table below. (Round answers to two decimal places)

Activity

Immediate

Predecessor(s)

Pessimistic

Probable

Optimistic

J

--

15

10

8

K

--

9

8

7

L

J

10

6

5

M

J

3

3

3

N

M

9

5

1

O

K, M

10

7

4

P

L, N

10

8

3

a) Calculate the expected duration, variance, ES, EF, LS, LF, and slack of each activity.

Use a table similar to the table below.

Task

Early Start

Early Finish

Late Start

Late Finish

Slack

t

variance

J

K

L

M

N

O

P

b) Calculate the expected duration and variance of the critical path.

c) Calculate the probability that the project will be completed in fewer than 24 time units.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!