Question: Consider the network described in the table below. Summarize your answers in the table below. Show all your work otherwise no credit given. Ten points

Consider the network described in the table below. Summarize your answers in the table below. Show all your work otherwise no credit given. Ten points (network 2 points, part a+b-6 points, part c-2 points). If using software as evidence of your work please provide relevant software output data.
\table[[Activity,\table[[Immediate],[Predecessor(s)]],Pessimistic,Probable,Optimistic],[A,--,15,10,8],[B,--,9,8,7],[C,A,11,6,5],[D,A,10,8,4],[E,B,D,9,5,1],[F,B,D,11,7,4],[G,C,E,12,8,3]]
a. Calculate the expected duration of each activity.
b. Calculate the expected duration and variance of the critical path.
ANSWERS:
 Consider the network described in the table below. Summarize your answers

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!