Question: Consider the Part Type Selection problem we covered in class. This problem helps us determine which parts we will produce in a new FMS .

Consider the Part Type Selection problem we covered in class. This problem helps us
determine which parts we will produce in a new FMS. The problem assumes that we have
candidate parts i=1,2,dotsN, that the total savings achieved by producing part i in the FMS
is si and that we know that there is a 'key bottleneck' in the FMS, which has P available time
units. Each part i requires a total processing time pi in the 'key bottleneck'.
In class we saw that a way to solve this problem is the following Greedy Heuristic:
Step 1: Order parts [1] to [N] such that
s[1]p[1]s[2]p[2]dotss[N]p[N]
Define remaining available time T=P
Step 2: For i=1dotsN select part i and add the part to the FMS if si>0iT=T-piP,QRipi,qiripi and si>0. Each
time you add a new part i, update the remaining available time asT=T-pi.
Now suppose you had 3 'key bottlenecks' (thatis3 resources that each might be the
bottleneck depending on the parts you choose to produce in the FMS). These resources
have P,Q and R time units available respectively. And each part i requires a total processing
time pi,qi and riin each of the three, respectively. Modify the algorithm above to solve the
3-bottleneck version of the problem.
TIP: In Step 1 you need to consider the processing times at all 3 stations todo the
ordering. In step 2, you must keep track of the remaining capacity at each station
separately.
 Consider the Part Type Selection problem we covered in class. This

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!