Question: Consider the partial resource loading chart shown below. Suppose that the maximum resource hours you can commit per day are 8. a. What are the

Consider the partial resource loading chart shown below. Suppose that the maximum resource hours you can commit per day are 8. a. What are the dates on which project resources are over allocated ? Answer As the maximum resource hours is 8 and as per below resource loading chart the over allocation occurs on the week of the 8lh through the 11*. Total hours allocated for each of these four days is nine . Project C alendar Dates June Activity 12345 39101112 1515171319 22 23 24 25 25 A 55555] B 2222 ] c 44444] D 33333 ] E 44444] F 22222 2 ] G 444] Total 66666 99997 66666 2444