Question: Consider the precedence diagram shown below, with activity duration ( days ) shown inside each node. For each activity, show the computed values of early

Consider the precedence diagram shown below, with activity duration (days) shown inside each node. For each activity, show the computed values of early start, early finish, late start, late finish, total float, free float, start float, and finish float.