Question: Consider the process described by the process flow diagram below. Each box describes an activity along with time required to carry out the activity, and

Consider the process described by the process flow diagram below. Each box describes an activity along with time required to carry out the activity, and the arrows show direction of the flow of material between activities.

The times for carrying out these activities are as follows: A 5 hours; B 10 hours; C 8 hours; D 4 hours; E 6 hours; F 3 hours.

Which of the following changes will reduce the minimum flow time (theoretical flow time) for a job by 4 hours?

Group of answer choices

Reducing time for B and D by 2 hours each

Reducing time for B and E by 2 hours each

Reducing time for C and E by 2 hours each

Reducing time for C and D by 2 hours each

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!