Question: Consider the process shown below to make a widget. The times shown below each task are the minutes per unit spent by 1 worker performing
Consider the process shown below to make a widget. The times shown below each task are the minutes per unit spent by 1 worker performing that task.
As shown in the diagram, initially only 1 worker is working at each station.
Note: Diagram is for the initial process and does not show the 2 new workers Bill and Jane.

Two new workers, Bill and Jane have joined the company and are to be assigned to the widget making process. The manager assigns both Bill and Jane to Station B. Bill takes 9 mins/unit and Jane takes 10 mins/unit. No existing workers are removed, when the two new workers are added.
What is the capacity of the entire process, after the 2 new workers (Bill and Jane) have been added to station B?
Station A 3 min/unit 1 worker Station B 7 min/unit 1 worker Station C 4 min/unit 1 worker Station D 5 min/unit 1 workerStep by Step Solution
There are 3 Steps involved in it