Question: Consider the project as outlined in the following table: Activity Normal Time Normal Cost (weeks) ($/week) Crash Costs Predecessor Crash Time (weeks) ($/week) A 7

Consider the project as outlined in the following

Consider the project as outlined in the following table: Activity Normal Time Normal Cost (weeks) ($/week) Crash Costs Predecessor Crash Time (weeks) ($/week) A 7 14 5 17 B 6 7 6 8 17 5 21 B D 5 14 18 N E 4 16 4 F F 6 12 3 15 D If the indirect cost savings are $ 20 per week, what would be the project length after crashing? Select one: A. 21 B. 20 C. 23 D. 19 E. 24