Question: Consider the project dependency matrix and activity durations in days provided below. URRERE A1 A2 A3 A4 A5 A6 A7 AB A9 A10 A11

Consider the project dependency matrix and activity durations in days provided below. URRERE A1 A2 A3 A4 A5 A6 A7 AB A9 A10 A11 A12 Duration A1 . X X 5 AZ X A3 X X A4 X AS X 11 A6 X X 5 A7 X 2 AS 3 . What is the shortest duration of this project (in days)? What is the critical path of this project? A9 X 4 A10 A11 A12 X 2
Step by Step Solution
3.45 Rating (155 Votes )
There are 3 Steps involved in it
To find the shortest duration of the project and the critical path we need to construct a network di... View full answer
Get step-by-step solutions from verified subject matter experts