Question: Consider the project described below and its corresponding AON network representation. After computing the ES, LS, EF, and LF times for each activity using the


Consider the project described below and its corresponding AON network representation. After computing the ES, LS, EF, and LF times for each activity using the CPM, answer the following question. - How much slack does activity 6 have? Ener only an integer number. You do not need to scan/upload any solution. Activity Duration Predecessor 1234567891710172721394818911,21,234,55,76,8