Question: Consider the project described below. Indirect project costs ( = $ 3 , 0 0 0 ) per day. ( No Late

Consider the project described below.
Indirect project costs \(=\$ 3,000\) per day.
(No Late Completion Penalties exist for this project)
Time left 0:47:46
If you need to crash two activities at the same time, for example, Activity \( A \) and Activity B, please enter \(\mathbf{A + B}\) without any spaces in between.
Path Durations
Activity to Crash
Additional
Cost
Cost
Savings
Net
Savings
ABCFG ABEG DEG
Total Cost Savings