Question: Consider the project described in the table below: Immediate Activity Duration Predecessor A 5 B 9 A 8 D 4 A E 6 B F

Consider the project described in the table
Consider the project described in the table below: Immediate Activity Duration Predecessor A 5 B 9 A 8 D 4 A E 6 B F 3 B.C G 6 CD una H 5 E,F,G What is the earliest start time (EST) and latest start time (LCT) of activity D? EST - 5 and LCT = 15 EST = 5 and LCT = 13 EST -5 and LCT = 14 EST = 5 and LCT = 16