Question: Consider the project described in the table below. What is the project's net present value? Cost of Capital Rate 12% Time 0 1 2 3
Consider the project described in the table below. What is the project's net present value?
Cost of Capital Rate 12%
Time 0 1 2 3 4
Cash Flows ($1,400) $200 $500 $800 $1,000
Select one: a. $382 b. $378 c. $371 d. $352