Question: Consider the project described in the table below: What is the earliest start time (EST) and latest completion time (LCT) of activity B? EST =9
Consider the project described in the table below: What is the earliest start time (EST) and latest completion time (LCT) of activity B? EST =9 and LCT=15 EST=9 and LCT=13 EST=9 and LCT=20 EST=9 and LCT=17
Step by Step Solution
There are 3 Steps involved in it