Question: Consider the project: Immediate Activity Day Estimates Crash Cost / Day Activity Predecessor Optimistic Most Likely Pessimistic A 2 6 8 $ 5 0 0
Consider the project:
Immediate Activity Day Estimates Crash CostDay
Activity Predecessor Optimistic Most Likely Pessimistic
A $
B $
C $
D A & B $
E B $
F D & C $
G E & C $
H F & G $
a Whats the probability that this project will be completed in days or less?