Question: Consider the project information in the following table. (time in days) Activity Predecessor Optimistic duration Normal duration Pessimistic duration A 5 6 7 B 8
Consider the project information in the following table. (time in days)
| Activity | Predecessor | Optimistic duration | Normal duration | Pessimistic duration |
| A | 5 | 6 | 7 | |
| B | 8 | 9 | 10 | |
| C | 1 | 3 | 5 | |
| D | C | 4 | 6 | 8 |
| E | A | 2 | 3 | 4 |
| F | B, D | 5 | 7 | 8 |
| G | C | 6 | 8 | 9 |
a) Calculate the expected time, ES, EF, LS, LF, slack time and variance for each activity (10 pts)
b) What is the expected completion time of the project? Explain. (5 pts)
c) Estimate the probability of finishing the project in 15 days or less (showing calculation)(5 pts)
d) What is the project completion time so that there is a 95% probability that the project will be finished by this time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock