Question: Consider the project of developing an optical simulator which has 6 different tasks. The tasks and task times are provided below in the following table:

Consider the project of developing an optical simulator which has 6 different tasks. The tasks and task times are provided below in the following table:

Activity

Time

Immediate Predecessor

A. Optical Design

3

-

B. System Performance Analysis

2

A

C. System Integration

5

A

D. Cost Analysis

2

B, C

E. Production Management

6

D

F. Long Lead Item Procurement

12

D

Using the information provided in the table, draw a network diagram using Arrow Diagramming Method (ADM).