Question: Consider the project plan diagram attached. There are six activities and two resources available, one of type A and one of type B , and
Consider the project plan diagram attached. There are six activities and two resources available, one of type A and one of type B andthey are available through the entire course of the project. The time and resource required to complete each activity is shown between nodes. For example, the activitythat connects node one with node two takes nine time periods to execute, and it takes one unit of resource A the entire time it's active.
With the assumption that you only have one unit of resource A andone unit of resource B availablecontinuously throughout the entire project, the resource loaded schedule shown below was developed. Note this constraint also determines the critical sequence of activities, which is indicated with red arrows. Resource A has a planned cost of $ per period, and Resource B has a planned cost of $ per period.
Now imagine that you have now reached the end of time period in this project. Activity is completed as scheduled, and Activity is also finished, two periods ahead of schedule. Resource A was expected to cost $ per period for periods. However, the actual cost was $ per period for periods. This means you are now ahead. In answering the questions below, remember that Resource A has a planned cost of $ per period of use, and Resource B has a planned cost of $ per period of use. Respond to the prompts at right.
What is the cost variance?
What is the new forecasted total cost at completion if you use Method
What is the new forecasted total cost at completion if you use Method
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock