Consider the project plan in the following table:

Consider the project plan in the following table: Activity Start End Duration (days) A 0 3 3 B 3 9 6 5 7 2 D 8 9 1 E 9 14 5 F 6 7 1 G 14 21 7 H 4 5 1 I 21 23 2 J 23 32 9 1- Construct the corresponding Gantt chart 2- What is the expected completion time of this project? NB: All the answers should be provided by your hand writing