Question: Consider the system that is given below. A,B,C are work centers, the planning horizon is 1 hr and assume that work centers work %100 efficient.
Consider the system that is given below. A,B,C are work centers, the planning horizon is 1 hr and assume that work centers work %100 efficient. What is the utilization of work center C? (If the answer is 23% just write 0.23 or 23 ). Answer: The bill of material for product X is shown below. The setup and run times required for Z (Setup time 25 minutes, Run time 4 minutes/unit), Y (Setup time 10 minutes, Run time 2 minutes/unit), and W (Setup time 20 minutes, Run time 3 minutes/unit) are given. Assume that Z,Y, and W are processed in the same work center and there is 170 working hours each month. And also assume that there is one setup for each product. How much X can be produced