Question: Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform
Consider the table below, which includes time and activity data for a Small IT Project. All duration estimates or estimated times are in days. Perform a critical path analysis for this project.
| Activity | Duration (Days) | Predecessor |
| A | 7 | - |
| B | 10 | A |
| C | 18 | A |
| D | 5 | A |
| E | 28 | B, D |
| F | 3 | C, E |
| G | 36 | E |
| H | 28 | B |
| I | 12 | F |
| J | 2 | H, G, I |
- Draw a network diagram representing the project. MS PowerPoint or Visio are good tools for this task. (10 points)
- Identify and list all of the paths through the network diagram and note how long they are. (4 points)
- What is the timeline within which the project can earliest be completed and explain why you say so? (3 points)
- If D takes 7 days, what will be the impact to the project and the critical path? Explain your reasoning. (4 points)
- If G takes an additional 7 days, what will be the impact to the project and the critical path? Explain your reasoning. (4 points)
Please give Unique answer