Question: Consider the task of installing a computerised system. The following table shows theactivities,timesandsequencesrequiredtoaccomplishthetask Activity to tm tp 1-2 2 4 12 1-3 2 4 25
Consider the task of installing a computerised system. The following table shows theactivities,timesandsequencesrequiredtoaccomplishthetask
Activity | to | tm | tp |
1-2 | 2 | 4 | 12 |
1-3 | 2 | 4 | 25 |
2-11 | 1 | 1 | 5 |
3-4 | 1 | 3 | 6 |
3-5 | 1 | 4 | 9 |
3-6 | 2 | 5 | 12 |
3-7 | 2 | 3 | 5 |
4-8 | 4 | 6 | 14 |
5-12 | 3 | 6 | 9 |
6-9 | 4 | 6 | 10 |
7-10 | 4 | 5 | 7 |
8-11 | 2 | 4 | 6 |
9-12 | 1 | 2 | 4 |
10-12 | 1 | 4 | 8 |
11-12 | 3 | 4 | 11 |
Required:-
- Drawanetworktorepresenttheabovedata
- Determinethecriticalpathoftheprojectandtheexpectedprojectlength