Question: Consider the time-phased budget for a project shown below: Activity ID Total PV 1 2 3 4 5 6 7 1 40 20 10 10
- Consider the time-phased budget for a project shown below:
| Activity ID | Total PV | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | 40 | 20 | 10 | 10 |
|
|
|
|
| 2 | 60 | 20 | 20 | 20 |
|
|
|
|
| 3 | 30 |
| 10 | 10 | 10 |
|
|
|
| 4 | 30 |
|
|
| 15 | 15 |
|
|
| 5 | 60 |
|
|
| 20 | 20 | 20 |
|
| 6 | 50 |
|
|
|
| 20 | 20 | 10 |
| Total PV by Period |
| 40 | 40 | 40 | 45 | 55 | 40 | 10 |
| Cumulative PV By Period |
| 40 | 80 | 120 | 165 | 220 | 260 | 270 |
- (40 points) Complete the status report for the end of period 4.