Question: Consider the time-phased budget for a project shown below: Activity ID Total PV 1 2 3 4 5 6 7 1 40 20 10 10

  1. Consider the time-phased budget for a project shown below:

Activity ID

Total PV

1

2

3

4

5

6

7

1

40

20

10

10

2

60

20

20

20

3

30

10

10

10

4

30

15

15

5

60

20

20

20

6

50

20

20

10

Total PV by Period

40

40

40

45

55

40

10

Cumulative PV By Period

40

80

120

165

220

260

270

  1. (40 points) Complete the status report for the end of period 4.