Question: Consider the time-phased work packages (cost in $1,000) and network diagram for the project baseline budget. Develop the project scheduled budget to answer the following
Consider the time-phased work packages (cost in $1,000) and network diagram for the project baseline budget.
Develop the project scheduled budget to answer the following questions.
Question 5 (5 points)
What is the project required budget in month 8?
Question 5 options:
|
|
12,500
|
|
|
21,000
|
|
|
19,000
|
|
|
28,000
|
|
|
15,000
|
Question 6 (5 points)
What is the project required budget in month 11?
Question 6 options:
|
|
18,000
|
|
|
4,000
|
|
|
25,000
|
|
|
12,000
|
|
|
9,000
|